Membrane bridge Floriade

Buitink Technology supplied and installed on behalf of AaDee Infrastructure Industry a tensioned membrane cover for the Floriade Bridge.

The Floriade membrane covered bridge has a total length of approximately 120 m, a width of 10 m and a height of approximately 4.5 m. The main bridge has a span of 60 m. The membrane bridge structure is equipped with a tensed membrane of approximately 1000 sqm.

To maintain the open character of the bridge, a relatively fine-meshed fabric has been used.

Project data

Material: Ferrari FT381
Architect: Gerard Extra
Main Contractor: Ballast Nedam
Contractor bridge: AaDee Infrastructure Industry BV
Stretched skin: Buitink Technology
Year of implementation: 2012